The second phase of
the Carrane Hill Wind Farm (Carrane Hill 2) consists of an additional
two Gamesa G52 turbines bringing the total installed capacity
to around 5MW.
The extension turbines
continue the existing row of the four Carrane Hill machines to
the northwest. Road access is provided by the main wind farm tracks
and the extension will export power via the existing export line
to the ESB substation at Corderry.