Slatbeg Wind Farm, lies on the lower northern slopes of the Slieve Beagh range within the townland of Fardross Mountain, which is situated in the old civil parish of Clogher. The relevant area lies within both the barony and ancient diocese of Clogher and the county of Tyrone. The site is centred on Ordnance Survey Grid Reference : H251000 Easting 346000 Northing and lies approximately 6 km to the south-west of the town of Clogher.

 

Aerial Photos

The site is surrounded by commercial forestry to the north, and west and covers just over 1km2 in area. The land use of the site reflects a significant degree of human activity. The predominant land use activity within the proposed development site is the grazing of animals although there is significant evidence of historic and recent turf cutting land use activity.


Layouts
The proposed wind farm will consist of 9 three bladed, horizontal axis, upwind turbines with a rotor diameter of nominally 84m, and a hub height of around 70m. The maximum ground to tip height will not exceed 112m. These machines will have a nominal generator rating of 2-2.5MW resulting in an overall site installed capacity of between 18 and 22.5MW.

Site Layout
 

Environmental Impact
A full Environmental Impact Assessment (EIA) has been undertaken which has included Landscape and Visual, Ecological, Archaeological, Hydrology, Geology and Noise Assessments for the wind farm. The assessments have been compiled into an Environmental Statement (ES) which was submitted accompanying a planning application for the wind farm in August 2006.

A non technical summary for the wind farm is available on request.

View from Clogher Village
View from A4 exiting Fivemile town

Turbine

 

Manufacturer and Model

TBC

Nameplate Rating

2000-2500 kW

Hub Height (Approximate)

70 m

Rotor Diameter (Approximate)

84 m

 

 

Site

 

Number of Machines

8

Total Installed Capacity

18 - 22.5 MW

Annual Output

58 GWh

Equivalent Tonnage of CO2 Saved*

58,000

Equivalent Number of Households

12,500

 

 

Power Contract

TBC

Commission Date (Scheduled)

TBC